1.0 Product Overview
(2)
(1)
(1) Backup connector
(2) Grid connector
(3)
(3) Grounding point
(4) PV switch
(4)
(5) PV + connectors / PV - connectors
(5)
(6) BAT + connector / BAT - connector
(7) Battery circuit breaker
(8) Communication ports
(9) Wi-Fi port
(6)
(10) LED display
(7)
(3)
2.0 Confirmation of Accessories and Tools
2.1 Scope of Delivery
Inverter (x1)
Side Cover (x1)
Cable Cover (x1)
6 Pin AUX Terminal
Backup Connector (x1)
Wi-Fi Module (x1)
Block (x2)
Power Cable between
Grounding Cable
Grounding Cable
two Column Series
between two Column
between Inverter and
Batteries (x1)
Series Batteries (x1)
1st Battery (x1)
2.2 (Optional) Accessories for Wall Mounting
Hook for Wall Bracket
Wall Bracket (x1)
Wall Anchor ST6*55 (x4)
(x4)
2.3 Installation Tools
Torx screwdriver
Bubble or digital level
Slotted screwdriver
Cord end
Crimping tool
Measuring tape
terminal crimper
3 .
T20
M5*12 (x7)
2.5Nm
5 .
T20
2
M5*12 (x4)
2.5Nm
1
4.0 Electrical Connection
Protect inverter with an individual grid / backup circuit breaker in order to ensure that the inverter can be
disconnected safely .
DANGER
Before making any electrical connections, please ensure the PV switch & all AC and BAT circuit breakers
are switched OFF and cannot be reactivated .
WARNING
Please refer to System Wiring Diagram for detailed wiring .
NOTICE
4.1 Grounding Connection
Additional
grounding point
T20
M5*12 (x1)
2.5Nm
Ø4~6mm²
8-10mm
4.2 Grid/Backup Connection
AC connection recommendation
Description
Max. Current
Breaker Type
Grid Side
21 .7A
32A
Backup Side
21 .7A
32A
Please follow local guidlelines for wiring
Quick Installation Guide
(RESERVE-INV-1-P10-L3-INT)
551943 Revision C - April 2024
(9)
(8)
(10)
PV MC4 Connector
Inverter Base (×1)
Grid Connector (x1)
Pair (×3)
Series Battery Main
Series Battery Main
Communication Cable
Positive Power Cable
Negative Power Cable
between two Column
(x1)
(x1)
Series Batteries (x1)
Screws and Grounding
PV&BAT Connector
Quick Installation Guide (x1)
Terminals Set (x1)
Disassembling Tool (x1)
System Wiring Diagram (x1)
Screw M5*12 (×18)
Small Spirit Level (×1)
Hexagonal screwdriver
Plier
Wire stripper
Multimeter
Disassembly and
Hammer drill
(DC voltage range
Assembly Tool of
(With a ∅10mm drill bit)
0-1000V)
PV connector
4 .
4
3
Inverter grounding
T20
point for battery
M5*12 (x1)
2.5Nm
Recommend cable cross section
6~8mm²
6~8mm²
3.0 Installing the Inverter
3.1 Before installing the inverter ensure that the batteries have been installed properly.
For more details refer to Battery Quick Installation Guide or Safety and Installation Instructions .
3.2 Mounting the Inverter on the Battery
1 .
2
3
T20
4
M5*12 (x6)
2.5Nm
1
3 .
T20
M5*12 (x4)
2.0Nm
1
2
3.3 Installing the Inverter Mounted with Wall Bracket
1 .
1
2
5
(x4)
Ø10mm
3
4
≥70mm
320mm
2 .
T20
M5*12 (x4)
2.0Nm
4.2.1 Grid Connection
1 .
2 .
L3 L2
L1 PE
Non-Insulated
Terminals (x5)
Ø4~6mm²
N
Ø13~17 .5mm
5 .
6 .
4.2.2 Backup Connection
The steps for backup connection are similar as grid connection .
2
1 .
2 .
1
AF2
1
L2
1.2±0.1Nm
3
L3
L1
2
N
PE
4.2.3 Disassembling Grid and Backup Connectors
Grid
1
Push to unlock
2.5mm
1
2
1
2
3
4.3 PV Connection
1 .
2 .
7mm
Ø4~6mm²
2 .6~2 .9Nm
Ø5-8mm
7mm
4 .
5 .
2 .
5
6
Guide
3
4
1
6
7
SW8
6.0Nm
3
2
3
4
1
3 .
2
4 .
AF2
1
L2
1.2±0.1Nm
3
L1
L3
N
PE
Align plug with socket
3 .
4 .
CLICK
Backup
1
Push to unlock
1
1
2
3 .
CLICK
Check the polarity of the PV strings
CLICK
Check the open-circuit voltage of the
PV strings which should be less than 950V
6 .
CLICK
CLICK
Guide
2
4
1
CLICK
2
2.5mm