Description
Energy meter with serial Modbus interface enables the
reading of all relevant data like meter reading, electricity,
voltage and power (active and reactive).
Technical data
Connection
Pic. 2
diagram
Dimensions
Pic. 3
Accuracy class
B according to EN50470-3,
1 according to IEC62053-21
Reference, Maxi-
I
= 5 A, Ima
ref
mum, initial current
operating voltage
3 × 230/400 V
Tolerance –20 %/+15 %
Counting range
000 000,0...9 999 999 kWh
LED-Ouptut
10 Imp/kWh
Connections
Conductor cross-section 1,5 - 16 mm
Main circuit
screwdriver pozi no. 1, slot no. 2,
torque 1,5 - 2 Nm
Connections
Conductor cross-section max. 2,5 mm
Control circuit
screwdriver pozi no. 0, slot no. 2,
torque 0,8 Nm
Operating
–25 ...+55° C (noncondensing
temperature
according standard EN50470)
Environment
Mechanical M2
Electromagnetic E2
Indicating elements
(Pic. 4)
Shows total consumption
T1total (kWh)
Shows partial consumption,
T1part. (kWh)
this value is resettable
CT
Shows the sett
current transformer ratio
Select
The transformer ratio can be
selected in Menu item Select, in
the open bridge Z1-Z2
Shows the instantaneous power
P (kW)
per phase or all phases
Shows the voltage per phase
U (V)
Shows the current per phase
I (A)
Shows the unit kWh when the
kWh
consumption is displayed
For P-, U-, I- or Error display, the
L1 / L2 / L3
corresponding phase is displayed
In case of missing phase or wrong
Error
current direction. The corresponding
phase is additionally displayed.
Notes before connecting
1. Do not connect L1, L2 or L3 to N
2. In order to avoid moisture in the meter due to
3. N must always be connected.
Attention!
These devices must only be installed by a professional
electrician, otherwise there is the risk of fire or the risk of
an electric shock.
Wiring diagram
6 A, Ist = 10 mA
x =
, 50 Hz
AC
This connection is to be fused according to the local instal-
lation instructions.
,
2
Operation of the LCD display
,
2
See page with LCD menu navigation.
The bridge Z1-Z2 should be removed for adjusting the
transformer ratio.
Installation instructions
The three-phase energy meter can be attached to a 35 mm
rail (EN60715TH35).
The meter can be used only in installation cabinets.
Declaration of Conformity CE
We, Honeywell Technologies Sàrl, 1180 Rolle, herewith
declare, on our own responsibility that the product:
which this certificate refer to, are in accordance with the
directive 2004/22/EG (MID) and the following standards:
Murten, 30.04.2013
Conformity Assessment Body:
Signed:
condensate build-up, acclimatise the meter at room
temperature for about half an hour before connecting.
The secondary, mains current transformer con-
nection is to be connected to the phase to be
measured and therefore the transformer don't
have to be grounded.
EEM400C-D-MO-MID
EN50470 parts 1 and 3 (electronic meter), of
October 2006.