Herunterladen Inhalt Inhalt Diese Seite drucken

Electrical Safety Check; Test Running - Zibro SC1226 Installationshandbuch

Vorschau ausblenden Andere Handbücher für SC1226:
Inhaltsverzeichnis

Werbung

Verfügbare Sprachen
  • DE

Verfügbare Sprachen

  • DEUTSCH, seite 1
CAUTION
After the confirmation of the above conditions, prepare the wiring as follows:
• Never fail to have an individual power circuit specifically for the air conditioner. As for the
method of wiring, be guided by the circuit diagram posted on the inside of control cover.
• The screw which fasten the wiring in the casing of electrical fittings are liable to come loose
from vibrations to which the unit is subjected during the course of transportation. Check them
and make sure that they are all tightly fastened. (If they are loose, it could cause burn-out of
the wires.)
• Check specification of power source.
• Confirm that supplied electrical capacity is sufficient.
• See to that the starting voltage is maintained at more than 90 percent of the rated voltage
marked on the name plate.
• Confirm that the cable thickness is as specified in the power source specification.
• Always install an earth leakage circuit breaker.
• The following would be caused by voltage drop: Vibration of a magnetic switch, which will
damage the contact point, fuse breaking, disturbance of the normal function of the overload.
• The means for disconnection from a power supply shall be incorporated in the fixed wiring and
have an air gap contact separation of at least 3mm in each active(phase) conductors.

ELECTRICAL SAFETY CHECK

It is advised to do the following safety checks.
Electrical safety check
Perform the electric safe check after completing installation:
1. Insulated resistance
The insulated resistance must be more than 2M
2. Grounding work
After finishing grounding work, measure the grounding resistance by visual detection and groun-
ding resistance tester. Make sure the grounding resistance is less than 4 .
3. Electrical leakage check (performing during test running)
During test operation after finishing installation, use an electroprobe and multimeter to perform the
electrical leakage check. Turn off the unit immediately if leakage happens. Check and find out the
solution ways till the unit operate properly.

TEST RUNNING

Perform test running after completing electrical safety check.
The test running time should last more than 30 minutes.
1.
Open the panel and lift the panel up to an angle which remains fixed. Do not lift the panel any fur-
ther when it stops with a click sound.
2.
Press the manual control button twice until the operating indicator lights up, the unit will operate
on Forced Cool mode.
3.
Check if all the functions works well during test running. Especially check whether the drainage of
indoor unit is smooth or not.
4.
Press the manual switch button again after finishing the test running . The operating indicator turns
dark and the unit stops operating and is now ready for use.
4
56
.

Werbung

Inhaltsverzeichnis
loading

Diese Anleitung auch für:

Sc1235Sc1246

Inhaltsverzeichnis