Applying the insulation:
1. Check that the insulation kit is complete (A).
2. Set up and align the storage vessel (A).
3. Place the shaped insulation panel for the lower dished end inside the support ring (for
500 – 750).
4. Lay the shaped insulation panel for the lower dished end around the support skirt
(500 - 750) or over the vessel feet (for 1000 – 3000) (B).
5. The double-sided adhesive tape included in the kit is to be applied vertically to the
vessel (150 mm to the left and right of the insulating jacket seam) (C).
6. Place and align the insulation over the storage vessel connections. Ensure that the top
of the insulation is flush with the top of the weld of the upper dished end (C/D).
7. Fit the insulation and check for a precision fit (D).
8. Pull off the adhesive film of the adhesive tape that has been applied to the vessel (E).
9. Fix the insulating jacket onto the adhesive tape that has been applied to the storage
vessel, ensuring that the holes in the insulating jacket are not warped (E)!
10. Starting from the top, peel away the adhesive films on both butt joint surfaces of the
insulating jacket and stick the surfaces to each other whilst applying slight pressure
(E).
11. Place and align the shaped insulation for the upper dishing end (F).
12. Remove the adhesive films on the surrounding area of the upper base insulation and at
the top of the insulating jacket in turn and stick both surfaces to each other whilst
applying slight pressure (F).
13. Do the same with the lower base insulation and then install the outer insulation of the
support ring (only 500 - 750 l).
14. Stick (all) the adhesive seams together with the adhesive tape included in the kit (H).
15. Any damage to the insulation is to be masked with adhesive tape.
16. Create the shaped pieces for the insulation around the connections (I).
3. Inspection & Maintenance
No liability shall be accepted for damage that is caused by failure to follow the installation
and operating instructions.
The storage vessel must be installed to allow easy access for maintenance, operation,
repairs or replacement. Site preparation and suitability for installation of the vessel are not
the responsibility of the manufacturer or the responsible distributor. Furthermore, facilities
for the secure drainage of the storage vessel in the event of any water leakage must be
provided to avoid water damage.
Constant topping up of the buffer tank poses a risk of corrosion. The storage vessel must
be included in the potential equalisation.
Removal
Once cooled, de-pressurize the system and remove the product from the system.
Local legislation must be adhered to when disposing of the various components.