c) Installing the support arm and mast clamps
Support arm
• Insert the support arm into the opening on the refl ector and slide it in
as far as it will go until it locks into place.
Mast clamp
• Slacken the winged nuts and bring the threaded U-bolt and
threaded clamp into installation position (see graphic on right).
Attach the parabolic refl ector to the mast or boom, at fi rst
loosely. Later on, the parabolic refl ector's azimuth will have to
be aligned.
• Tighten the screw connectors between mast clamp and
antenna support fi nger-tight (for CCA 600/x spanner size 10,
for CCA 750/x and 850/x spanner size 13), loosen if required.
Later on, the parabolic refl ector's elevation will have to be
aligned.
d) Installation feed system support
•
Remove the clamp from the pre-feed system support, loosen
the screw and insert the feed system. Close the clamp and
tighten the screw slightly. The feed system may need to be still
set to the polarisation. Please refer to the application note of
the feed system.
e) Feed system (LNB)
The feed system(s) and instructions for their installation are
not included in the scope of supply of the parabolic anten-
na. For more detailed information on their correct installation
please refer to the manuals supplied with the respective feed
system.
•
Example for the installation positions for a multi-feed applica-
tion with up to 10° satellite spacing using the multi-feed
support CCZ 02 (possible with CCA 750/850):
Pos. 1
ASTRA 19,2° East
EUTELSAT 16° East
EUTELSAT 13° East
Tip:
For multi-feed applications the antenna should be aligned
towards the satellite which is transmitting the weakest signal
level.
Pos. 2
EUTELSAT 13° East
EUTELSAT 10° East
EUTELSAT 7° East