VII. Testing
1 1 1 1 . . . . Inspection before use
A. Check installation of the whole machine and the pipe connections
according to the pipe connecting drawing;
B.
Check the electric wiring according to the electric wiring diagram; and
earthing connection;
C.
Make sure that the main machine power switch is off;
D. Check the temperature setting;
E.
Check the air inlet and outlet.
2 2 2 2 . . . . Trial
A. The user must "Start the Pump before the Machine, And Turn off the
Machine before the Pump", or the machine will be damaged;
B.
The user should start the pump, check for any leakage of water; and then
set suitable temperature in the thermostat, and then switch on power
supply;
C.
In order to protect the swimming pool heater, the machine is equipped
with a time lag starting function, when starting the machine; the blower
will run 1 minute earlier than the compressor;
D. After the swimming pool heater starts up, check for any abnormal noise
from the machine.
9