6

Commissioning

6.1 Preconditions for commissioning

The PV Next String Combiner Box is fully mounted.
► Before commissioning, check that the product is not
damaged.
If the enclosure, printed circuit board or individ-
ual components are damaged or heavily soiled,
do not operate the product. Contact your Weid-
müller representative or distributor.
During commissioning, ensure that no moisture,
dust or foreign objects can penetrate into the
product.
Two procedures are permitted for installation
work:
– Working on live components: Only electricians
who are qualified to work on live components
may work under voltage. They must comply
with local regulations (e.g. personal protective
equipment and risk assessment).
– Voltage-free working: Input and output cables
must be properly disconnected and secured
against being switched on again. Voltage-free
work may be carried out by electricians and
trained personnel.
► Refer to the inverter manufacturer's documen-
tation.
The Weidmüller WM4C and PV-Stick PV connectors are
compatible with each other. Weidmüller accepts no liability
for damage caused by the use of connectors from other
manufacturers.
40
6.2 Commissioning the PV Next String Com-
biner Box
Imminent risk to life!
Work on live components may only be carried
out by qualified electricians.
► Observe the country-specific regulations for
working on live components.
► When working on live components, always
use suitable tools and aids that eliminate
the risk of electric arcs and electric shocks.
Imminent risk to life!
Up to 1,000 V DC can be present on live parts.
► Make sure that the voltage is not restored
until the work has been completed.
► Switch off the inverter. If there is a switch-disconnector
on the inverter, it must be in the off-position.
► If there is a switch-disconnector on the PV Next
String Combiner Box, it must be in the off-position.
► Insert the functional earth cable and the remote signal-
ling cable into the enclosure.
► Disconnect the functional earth cable, crimp a wire-end
ferrule onto the cable and connect it.
► Disconnect the wires of the remote signalling cable,
crimp the wire end ferrules onto the wires and connect
them to the terminal of the remote signalling contact.
► Check that all cables are connected with the correct po-
larity.
► Carry out the further steps according to your product
variant.
DANGER
DANGER