STEP 1B - Only required if table is not 1600mm (63") wide
Adjust the cross channels to their final lengths
• Use the 5mm Allen key to loosen the (8) set screws on the inward side of the
cross channels.
• Expand or contract the cross channels until flush with both ends of the desk.
Free cables as necessary to allow the frame to adjust.
• Ensure proper alignment to predrilled holes on the desktop.
• Once properly adjusted, use the 5mm Allen key to re-tighten the set screws
(8 total).
STEP 2
Adjust the position of the frame before attaching it to the table.
• Check that the top supports on each side are flush to both ends of the desktop
and align to the predrilled holes on the desktop.
• The rear cross channel will be 240mm (9.5") for 800mm (31.5") Depth Tops
from the rear of the table.
STEP 3
Attach base to the table
• Use the M6 Phillips round head screws (10 total required) and a Phillips screwdriver.
• The screws fit through guides in the top of the supports and cross channel.
Ensure proper alignment with predrilled holes on the desktop.
• Using two people, flip the Base and Table upright.
• Attach clamp covers to each side. Start by placing the smaller piece on the inside
of the clamp bracket. Align the larger piece and apply pressure to secure.
ACCESSORY INSTALLATION
STEP 1
Cable Management
• Position the cable tray in the center of the table towards the rear and align
with pre-drilled holes on the desktop.
• Attach the cable tray with (4) M6 Phillips round head screws. The open end
should face the rear.
• Use the additional provided cable management as needed.
• Cables must not interfere with table operation.
• Cables must not interfere with the user.
Rear
240mm (9.5")
Front
Rear
Front