This kit, mat. no. 07493370 for PW 6163, contains the following:
2 pre-installed feet
2 pre-installed front panels
2 side panels
8 raised-head screws, 6 x 16
1 information sheet
These installation instructions
List of illustrations:
Fig. 1, side panel and service panel removal
Fig. 2, floor bracket removal
Fig. 3, foot installation
Fig. 4, front and side panel installation
Disconnect the machine from the steam supply (if applicable) and electric supply, and ensure that utilities cannot be switched on
again in error.
Remove the 2 side panels and 2 service panels, Fig. 1.
Unscrew the machine's floor fastening.
Note
If applicable, remove any spacer plates that may be in use and take care to note the number installed and their positions so that
they can be reinstalled in an identical manner.
Disconnect the floor drain.
Use a suitable lifting aid (e.g., pallet truck and suitable wood blocks) to raise the machine by approximately 200 mm.
Danger!
Take suitable measures to ensure that the machine cannot fall
Unscrew the 4 floor mountiing brackets, Fig. 2, Pos. 1.
Install the pre-installed feet (Fig. 3, Pos. 2) on the left and right under the machine base frame and screw them in position.
(On each corner, 2 screws from the inside and 2 screws from the bottom; see Fig. 3, Pos. 3.)
Extend the connection between the machine drain outlet and the on-site drain by approximately 170 mm.
Lower the machine and return it to its original position.
Check that the machine is perfectly level in all directions.
If necessary, level the machine by installing spacer plates as appropriate.
Install the floor mounting bolts through the brackets in the existing holes, Fig. 4, Pos. 1.
Install the 2 stand front panels (Fig. 4, Pos. 2) at the front and back, and align them with the corners of the machine.
Install the 2 stand side panels (Fig. 4, Pos. 3). Readjust the 2 front panels, if necessary.
Reinstall the 2 side panels and 2 service panels.
Carry out appropriate electrical safety checks.
Reconnect the machine to the power supply and the steam supply (if applicable).
am
10.05.2010
Diese Unterlagen dürfen ohne unsere Genehmigung weder vervielfältigt noch Dritten zugänglich gemacht werden. Eigentumsrechte vorbehalten.
Umbau- und Montageanweisung
M.-Nr. 07564360

Werbung

loading

Diese Anleitung auch für:

Ug 6163Ug 6323Ug 6243