Start initialisation run
For the 6-key hand switch, there are two options for starting an initialisation run.
1. The initialisation run is requested by the control:
• The display shows "Start the initialization?". Confirm it with
function key 1.
-›› The initialisation run was started and can now be performed.
2. Manually start the initialisation run:
• Press the "M" key to open the menu.
• Select the "Control" menu item.
• Enter the password "13121" using the function keys and the "UP" and
"DOWN" keys.
• If drive group management is activated, you must first select the
corresponding group.
• Select the "Startup" menu item.
• Select the "Start the initialization" menu item.
-›› The initialisation run was started and can now be performed.

Performing an initialisation run

The display of the hand switch shows the
number of detected drives (see
Figure 10).
Is the number not correct?
• Check the connections of the controls as well as the mains plug.
Is the number correct?
• Confirm this with function key 1.
-›› An arrow pointing down will appear on the display.
• Press the "DOWN" key and keep it pressed until all drives have moved to
the lower end position.
MultiControl II duo and MultiControl II quadro assembly instructions
Figure 10 - Initialisation run

Quicklinks ausblenden:

Werbung

Kapitel

Inhaltsverzeichnis
loading

Diese Anleitung auch für:

Rk multicontrol ii quadro

Inhaltsverzeichnis